Two major projects aimed at strengthening Mongolia’s energy security and fuel supply have returned to the spotlight. On October 8, the first meeting of a task force established to accelerate the country’s oil refinery project was held. Meanwhile, plans were announced to restart the process of selecting a private investor for the 450 MW Tavan Tolgoi power plant.
Both projects are strategically important to reducing Mongolia’s energy dependence and securing reliable domestic supply. However, years of delays demonstrate that the country’s challenge lies not simply in launching new initiatives, but in delivering projects that have already been started.
Oil Refinery: Moving Beyond 60% Completion
Launched in 2018 in Altanshiree soum, Dornogovi Province, Mongolia’s oil refinery project is designed to process 1.5 million tonnes of crude oil annually. The project is financed in part through a USD 1.7 billion line of credit from the Government of India, and its expected commissioning date has been postponed to 2028.
Construction is reportedly around 60% complete. However, the limited progress over an extended period highlights the need for more detailed reporting on construction milestones, the causes of delays, and the remaining work required to bring the refinery into operation.
Even once operational, the refinery will not meet Mongolia’s entire fuel demand. With domestic demand potentially reaching four million tonnes annually, a refinery with a capacity of 1.5 million tonnes would cover only part of the country’s needs. The project could significantly reduce dependence on imported fuel, but it would not eliminate that dependence entirely.
Establishing a task force to accelerate implementation is a useful first step. Delivering tangible progress, however, requires measurable targets for each remaining phase, including construction, financing, equipment procurement, commissioning, and the final operational deadline.
Tavan Tolgoi Power Plant: Another Search for an Investor
The proposed 450 MW Tavan Tolgoi power plant is intended to provide a reliable electricity supply for major mining operations and help ease pressure on the wider energy system. Yet the project has faced years of challenges involving investment, procurement, financing, legal disputes, and changes to its implementation model.
Marubeni was selected in 2016, but financing issues remained unresolved. A state-financed construction model was subsequently considered, and legal disputes followed a tender announced in 2023. In 2026, the possibility of selecting a private investor has once again emerged.
This history illustrates that selecting an investor is only one component of project delivery. Unless the investment model, financing arrangements, power purchase agreement, tariff structure, risk allocation, and government obligations are clearly defined, replacing the investor may simply lead to another cycle of delays.
Mongolia continues to import electricity to meet domestic demand. Delays to a power plant of this scale are therefore not merely a construction issue; they directly affect industrial production, mining operations, household consumption, and national energy security.
The Core Problem Is Not Just Financing, but Project Delivery
Financing constraints can contribute to delays in strategic projects, but they are not the only cause. Changes in government can lead to shifting implementation models, prolonged decision-making, unclear accountability, and insufficient long-term assurances for investors. These factors increase project risk and undermine investor confidence.
For a power plant, investors need certainty about who will purchase the electricity, at what tariff, and for how long. Without a long-term, financially viable power purchase agreement, it becomes difficult to forecast project revenues and establish a reliable basis for debt repayment.
At the same time, when electricity tariffs are regulated below cost-recovery levels, investment in new generation capacity can become more difficult to finance. Tariff policy, consumers’ ability to pay, government subsidies, and the conditions for private investment must therefore be considered together.
International experience suggests that successful private investment depends on clear project rules, well-defined contractual terms, transparent tariff methodologies, credible government commitments, and an appropriate allocation of risk. Conversely, if the government assumes excessive obligations to pay for electricity that is not actually consumed or capacity that is not utilized, the project could create additional fiscal liabilities.
Policy Recommendations
1. Publish monthly progress reports on both projects.
The government should establish publicly accessible online dashboards for the oil refinery and Tavan Tolgoi power plant. These should report construction progress, financing disbursed, schedule changes, outstanding obstacles, responsible institutions, and upcoming milestones.
2. Ensure a transparent and competitive investor selection process.
The selection of a private investor for the Tavan Tolgoi power plant should involve independent advisers with international experience and follow a transparent, competitive process. Evaluation criteria, financing requirements, and the principal contractual terms should be established in advance to strengthen investor confidence and public accountability.
3. Structure power purchase agreements to support viable financing.
Power purchase agreements should enable projects to secure financing while allocating payment obligations and risks appropriately among the government, private investors, and consumers. Long-term electricity demand from major users, including Oyu Tolgoi and Tavan Tolgoi, should be incorporated into national energy planning.
4. Establish a time-bound completion plan for the oil refinery.
The remaining work should be divided into clearly defined phases with firm deadlines. Financing, construction, equipment delivery, commissioning, and operational readiness must be coordinated under a single implementation schedule.
5. Strengthen institutional continuity for strategic projects.
Mongolia should establish institutional arrangements that preserve the core objectives, implementation principles, and contractual accountability of strategic projects across changes in government. This would reduce policy uncertainty and help prevent repeated changes in direction.
Conclusion
The oil refinery and Tavan Tolgoi power plant are strategic investments that could strengthen Mongolia’s energy security. However, launching a project, establishing a task force, or searching for an investor does not constitute success in itself.
Success must be measured by actual construction progress, adherence to commissioning schedules, efficient use of financing, additional energy generated, and measurable reductions in dependence on imports.
Mongolia needs more than new initiatives. It needs institutions that deliver on decisions, maintain policy continuity, and report results transparently.